define your time and cost budget metrics and amounts

Info

Budgets are a great tool for keeping a handle on how well your engagements are performing and notifying you when things change. For example, the most my employees can spend on this engagement is $5000. Please track my disbursed costs and notify me when I have consumed 75%, 90%, and 100% of my allocated budget. You can also use budgets along with Projector forecasting to know not only the budget status as of today, but how things are looking by project completion too. Use budgets to identify performance problems early and make corrections.

The Engagement Budget tab is where you define your time and cost budget metrics and amounts. You can then view performance to this budget on your Project Dashboard or in reports. Time and expenses are submitted against projects, not engagements, therefore the numbers against the engagement budget are a rollup of the projects underneath it. Because of this Projector also shows all your project budgets on this tab as read only. To edit a project's budget you will need to visit its budget tab

The engagement budget editor is reached by opening an engagement or project from either the Project Dashboard or the Project Browser. Then select the Engagement Tab | Budget Subtab.

 


Permissions and Settings

In order to edit the engagement budget, you must be the Engagement Manager on the engagement and the Edit Engagement Budgets stage permission must be ticked for the current stage. 

...

 First choose from one of the following metrics. There are separate choices for Time and Expense.

 


Time Metrics

For the time tab, the following metrics are available.

Time Metric

Description

Billing Adjusted Revenue

A money amount that is equal to the amount your client will be charged

Contract Revenue

A money amount that is based on your contract's negotiated rates

Resource Direct Cost

A money amount that reflects the internal cost of your resources

Chargeable Hours

An hours amount for each hour that has positive billing adjusted revenue

Hours

An hours amount for each hour approved

...


Cost Metrics

For the cost tab, the following metrics are available.

Cost Metric

Description

Client Amount

The amount that the client is charged. Remember that expenses can be written up or written down, so they will not necessarily match the disbursed amount.

Disbursed Amount

The out of pocket amount for expenses

Expense Amount

The amount born by the company. If the client can only be charged half of an expense, then the other half is born by the company.

...


Then enter a budget amount. Depending on the metric type you will enter either a money amount or an hours amount.

...

You will also notice in this screenshot that each project has two rows. One for Billing Adjusted Revenue and one for Contract Revenue. This is because unlike engagement budgets, projects can have multiple metrics. 

Customize View

From the dropdown choose your Summary Performance to Budget. The option you choose reflects how you wish to look at the engagement's performance.

 


When calculating Actuals to Date and Estimate to Complete, you can optionally include unapproved hours and requested hours by ticking a checkbox.

  • Unapproved time in actuals to date - for time periods up to the Use Actuals Through Date, include submitted time in addition to approved time (but not draft time)
  • Requested hours in estimate to complete - for time periods after the Use Actuals Through Date, use the current requested hours instead of the current booked hours


Summary Type

Description

Estimate at Completion

An estimate at completion is based upon the work you have done so far, plus the work you have booked. This is useful for flagging when a project is starting to go over budget.

Actuals to Date

Actuals to Date represent the work you have done so far. This is useful for letting your managers know when your budget has been burned up by a certain amount. For example, when half your budget has been consumed.

In addition you specify the Use Actuals Through Date here. Please see the help link for more information about this date.

...

The following tables describe the grids shown.

Current State Grid

Current State (ATD)

Description

Engagement/Project

Engagement code/name or project code/name.

Actuals to Date

Actuals consist of Approved time or cost cards up to the date in the grid header

Estimate to Complete

Projections consist of Booked time or Planned costs after the date in the grid header

Estimate at Completion

The total of the Actuals to Date and Estimate to Complete.

Performance to Budget Grid

Performance to Budget (ETC or ATD)

Description

Estimate at Completion

The total of the Actuals to Date and Estimate to Complete.

Budget

See the budget section discussed above for more information.

Metric

See the metric section discussed above for more information.

Budget Variance

The difference between the

% Budget Variance

The difference between the Estimate at Completion amount and the budget and reflects the amount by which it is estimated that the budget will be off.

Budget Status

Reflects the current budget status according to your budget alerts

...