PwsProjectTask

Overview


This structure represents a project task, and includes information about the task relevant to time entry.

Format


PwsProjectTask
  • PwsProjectTask
    • ExternalSystemIdentifier: String (50)
    • ProjectTaskId: Int32
    • ProjectTaskUid: Int64
    • Description: String (1000)
    • Name: String (512)
    • Notes: PwsProjectTaskNoteHistory []
    • OpenForTimeFlag: Boolean
    • ParentProjectTaskIdentity: PwsProjectTaskRef
    • ParentTaskName: String (512)
    • PlannedEndDateTime: DateTime
    • PlannedStartDateTime: DateTime
    • ProjectTaskTypeIdentity: PwsProjectTaskTypeRef
    • Roles: PwsProjectTaskRole []
    • SequenceNumber: Int16
    • WbsCode: String
    • ParentTaskWbsCode: String

Elements


Element

Data Type

Description

Sample Data

ExternalSystemIdentifier

String (50)

The external system identifier is a unique identifier for a project task.


ProjectTaskId

Int32

The project task id is a unique identifier for a project task. For internal use only.  


ProjectTaskUid

Int64

A unique and immutable identifier for a project task.

1152921504608644258

Description

String

The project task description.


Name

String

The project task name is a unique identifier for a project task. This is the name resources will see when choosing tasks to enter their time against. Multiple tasks in the same task plan may share the same name, as long as they are under different parent tasks. The Work Breakdown Structure (WBS) code will differentiate between like-named tasks.

Task A1

Notes

PwsProjectTaskNoteHistory []

The project task notes


OpenForTimeFlag

Boolean

If set to 'true', resources are able to submit time using this Task.

true

ParentProjectTaskIdentity

PwsProjectTaskRef

The identity of the parent task. This will be null for root-level tasks.


ParentTaskName

String

The name of the parent task.

Task A

PlannedEndDateTime

DateTime

The planned end date of the task (in UTC format). For this purpose, days start at midnight so a time component of 4:00AM indicates that the task ends mid-day (assuming an 8 hour day).

2018-03-30T08:00:00Z

PlannedStartDateTime

DateTime

The planned start date of the task (in UTC format). For this purpose, days start at midnight so a time component of 4:00AM indicates that the task starts mid-day (assuming an 8 hour day).

2018-03-01T00:00:00Z

ProjectTaskTypeIdentity

PwsProjectTaskTypeRef

The project task type associated with the project task.


Roles

PwsProjectTaskRole []

The project role(s) associated with the project task.


SequenceNumber

Int16

This field determines the overall position of the task within the task plan. Tasks are ordered according to their work breakdown structure (WBS code).

1

WbsCode

String

The project task work breakdown structure code is a unique identifier for a project task.

1.1

ParentTaskWbsCode

String

The work breakdown structure of the parent task.

1

Usage Example(s)


Example 01
                      <a:PwsProjectTask>
                        <ExternalSystemIdentifier i:nil="true" xmlns="http://projectorpsa.com/DataContracts/Shared/Common/"/>
                        <ProjectTaskId i:nil="true" xmlns="http://projectorpsa.com/DataContracts/Shared/Common/"/>
                        <ProjectTaskUid xmlns="http://projectorpsa.com/DataContracts/Shared/Common/">1152921504608644258</ProjectTaskUid>
                        <a:Description i:nil="true"/>
                        <a:Name>Task A1</a:Name>
                        <a:Notes/>
                        <a:OpenForTimeFlag>true</a:OpenForTimeFlag>
                        <a:ParentProjectTaskIdentity xmlns:b="http://projectorpsa.com/DataContracts/Shared/Common/">
                           <b:ExternalSystemIdentifier i:nil="true"/>
                           <b:ProjectTaskId i:nil="true"/>
                           <b:ProjectTaskUid>1152921504608637335</b:ProjectTaskUid>
                        </a:ParentProjectTaskIdentity>
                        <a:ParentTaskName>Task A</a:ParentTaskName>
                        <a:PlannedEndDateTime>2018-03-30T08:00:00Z</a:PlannedEndDateTime>
                        <a:PlannedStartDateTime>2018-03-01T00:00:00Z</a:PlannedStartDateTime>
                        <a:ProjectTaskTypeIdentity xmlns:b="http://projectorpsa.com/DataContracts/Shared/Common/">
                           <b:ExternalSystemIdentifier i:nil="true"/>
                           <b:ProjectTaskTypeId i:nil="true"/>
                           <b:ProjectTaskTypeUid>1152921504608115974</b:ProjectTaskTypeUid>
                        </a:ProjectTaskTypeIdentity>
                        <a:Roles>
                           <a:PwsProjectTaskRole>
                              <ProjectRoleIdentity xmlns="http://projectorpsa.com/DataContracts/Shared/Common/">
                                 <ExternalSystemIdentifier i:nil="true"/>
                                 <ProjectRoleId i:nil="true"/>
                                 <ProjectRoleUid>1152921504609522500</ProjectRoleUid>
                              </ProjectRoleIdentity>
                              <ProjectTaskIdentity xmlns="http://projectorpsa.com/DataContracts/Shared/Common/">
                                 <ExternalSystemIdentifier i:nil="true"/>
                                 <ProjectTaskId i:nil="true"/>
                                 <ProjectTaskUid>1152921504608644258</ProjectTaskUid>
                              </ProjectTaskIdentity>
                              <ProjectTaskRoleId i:nil="true" xmlns="http://projectorpsa.com/DataContracts/Shared/Common/"/>
                              <ProjectTaskRoleUid xmlns="http://projectorpsa.com/DataContracts/Shared/Common/">1152921504608549425</ProjectTaskRoleUid>
                              <a:ActualMinutesSinceAsOfDate>0</a:ActualMinutesSinceAsOfDate>
                              <a:BudgetedMinutes>10560</a:BudgetedMinutes>
                              <a:CompletedFlag>false</a:CompletedFlag>
                              <a:Estimates/>
                              <a:LateFlag>false</a:LateFlag>
                              <a:TotalMinutesToDate>0</a:TotalMinutesToDate>
                              <a:CompletedFlagAtLatestPostAsOfDate i:nil="true"/>
                              <a:LateEligibleFlag>false</a:LateEligibleFlag>
                              <a:LatestAsOfDatePostDateRange i:nil="true"/>
                              <a:RemainingMinutesPostDateRange i:nil="true"/>
                              <a:RemainingMinutesPriorToDateRange>10560</a:RemainingMinutesPriorToDateRange>
                              <a:TotalMinutesPostTimesheet>0</a:TotalMinutesPostTimesheet>
                           </a:PwsProjectTaskRole>
                        </a:Roles>
                        <a:SequenceNumber>1</a:SequenceNumber>
                        <a:WbsCode>1.1</a:WbsCode>
                        <a:ParentTaskWbsCode>1</a:ParentTaskWbsCode>
                     </a:PwsProjectTask>