Including or excluding a milestone resets approvals.

You cannot edit milestones from this screen. To make edits please use the contract line item editor.

Browse all CLIs associated with this invoice from the appropriate contract line item dropdown box. A CLI is included in this list based on Invoice Scope. For example, if you invoice at the engagement level then all contract line items under that engagement are listed here.

...

Field

Description

IncludeTick the checkbox to include milestone on this invoice. Disabled for pending or already invoiced milestones.
Name / DescriptionName of the milestone and description. Click To edit these click the link to edit and do so from the milestone editor.
Contract Line ItemName of the contract line item and it's code. Click To edit these click the link to edit and do so from the contract line item editor.
Project Code / Task

The project associated with this milestone. Useful if you invoice your clients at the project level, when viewing reports broken down by project, or when using the Project Dashboard.

When you tie a task to a milestone it drives the pending and achieved dates.

PO NumberComes from Contract Line Item - Setup Contract Line Item
AmountThe amount that the client should be invoiced for this milestone. Use a negative amount to issue a credit memo.
Status

The following status' are available

  • Pending - not yet achieved
  • Foregone - has not and will not be achieved
  • Achieved - been achieved, but not yet invoiced
  • Invoiced - on an unissued invoice
  • Billed - on an issued invoice

The status is set automatically except for Pending/Foregone. You can choose between Pending/Foregone as long as the milestone is unachieved.

Achieved DateThe date the milestone was actually achieved. Once a milestone is achieved you can no longer edit any other settings. If you wish to go back and make changes, clear the achieved date or remove the complete flag from the associated task.