Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

ColumnDescription
Bullet The bullet turns yellow when a task is over budget. A task is over budget when hours at completion are greater than the budgeted hours.
HrsToDateThe number of hours approved against this task
% CompHow complete is this task? The percent is auto-calculated based on the number of reported hours, but resources can override the percent complete manually through Enter Time Entry. For example, if ten hours have been approved for a twenty hour task, it is 50% complete. However, the resource has the option to step in and say the task is actually 75% done.
Hours RemainThe number of hours required to complete the task. This number is derived from approved hours to date and percent complete. For example, if you have worked 10 hours and are 50% complete, you have 10 hours left.
Hrs at Compl

For completed tasks this is just the number of hours spent.

For in progress tasks it is the estimated hours required that will have been spent by the time the task completes.

Budgets HoursThe quantity of hours budgeted for this task, as determined by the Task Plan.

Budget Variance Image Modified

The percent of variance between the budgeted hours and estimate to complete hours. Projector displays a shader bar in red/green so that you can visualize how over or under budget a task is.

...

ControlDescription
Active BaselineThis is just another access point to the same dropdown in the main Task Status window. It is not very useful.
Display Performance to Schedule

Toggle display of the the Gantt chart

Display Performance to Budget

Toggle display of the numbers grid.

Use Actuals Through DateAgain, the same as the button on the main screen. Not that very useful here.

...