Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

When using the action in the Task Planning > Resource Plan tab to Request or Book hours from task hours, Projector will use this setting of whether you're looking at task hours planned or task hours remaining to create a request or a booking. That is, in the example above, when you use the action to translate task hours into requested or booked hours, Projector will request or book 40 hours for the second week if you're using task hours planned or 20 hours for that week if you're viewing task hours remaining.

...