Whether you’re initializing your Smartsheet sheets from a template or using an existing sheet, there are a few required fields you need to include for Projector and Smartsheet to properly share data.
When troubleshooting a sheet or template, Projector Support will have very limited visibility into Smartsheet-specific issues and may ask you to share your sheet, template, or workspace with the following email address - ppsa-supportuser-smartsheet@projectorpsa.com
Get Starter Templates from Projector
If you’d like to get a head start on creating Smartsheet templates and sheets, there are two options.
Share the Smartsheet workspace you reference above with ppsa-supportuser-smartsheet@projectorpsa.com
Send the email address associated with your Smartsheet User and ask Projector support to temporarily share a Projector Templates workspace with you.
Required Fields for Smartsheet Sheets and Templates
Field | Type | Notes |
---|---|---|
Task Name | Text/Number | Default column used by Smartsheet at the Primary Column |
Duration | Duration | Default column used by Smartsheet for schedule calculations |
Start Date | Date/Time | Default column used by Smartsheet for schedule calculations. |
End Date | Date/Time | Default column used by Smartsheet for schedule calculations. |
Predecessors | Text/Number | Default column used by Smartsheet for schedule calculations. |
Assigned To | Dropdown list (multi-select, restrict to list values only) | Note that this is not a contact list type field that Smartsheet uses by default. Replace the contact list field of the same name with a dropdown list to use for role assignment. If you chose to embed roles in a template or sheet, surround them with parentheses in order that Projector can interpret them as roles. |
% Allocation | Text/Number | Projector requires that a “% Allocation” field be populated (likely with a formula) so that Projector can properly synchronize. |
Open for Time | Checkbox | Time Entry will only display task that have the “Open for Time” value checked. |
Task Type | Dropdown list (single-select, restrict to list values only) | Projector requires each task to have a task type. If a task type is not selected prior to a sync, one will be selected automatically. |
Other columns… | Your sheet can contain additional columns beyond those mentioned above, but Projector requires the above fields in order to sync properly. Any additional data will not be sync’d to Projector, but will remain in the sheet for your planning purposes. |
Optional Integrated Projector Fields for Smartsheet Sheets and Templates
In addition to the required fields above, Projector will also synchronize data from Projector to Smartsheet for these additional integrated-enabled fields when they are included in a linked sheet. You will notice that each of the following fieldnames ends with “(PPSA)”. During a synchronization event, these special (PPSA) designated fields will populate with data calculated by Projector. If you add these fields to your templates or linked sheets, it is recommended that you set them as read-only in the sheet.
Field | Type | Notes |
---|---|---|
WBS Code (PPSA) | Text/Number | Populates with the Work Breakdown Structure (WBS) Code resources will see on their timesheets. |
% Complete (PPSA) | Text/Number | Populates with the Projector-calculated percent complete for the current task. This value will reflect approved timecards for the task in question. Note: If you update the sheet settings to use this field to track % Complete, your Gannt charts will also reflect this value |
Remaining Minutes (PPSA) | Text/Number | Populates with the Projector-calculated remaining work minutes for the current task. This value will reflect approved timecards for the task in question. Fun with formulas: Work minutes remaining may not be an easy to interpret value. However, if you include this field as a hidden field, you can create an “Remaining Time” field that intelligently calculates hours, days, weeks, or maybe all of the above with a cleverly crafted column formula. |
Worked Minutes (PPSA) | Text/Number | Populates with the Projector-calculated worked minutes for the current task. This value will reflect approved timecards for the task in question. Fun with formulas: As with remaining minutes, worked minutes may not be an easy to interpret value. A carefully crafted formula that refers to a hidden “Worked Minutes (PPSA)” field could certainly show a better representation of “Time Worked” or “Time Entered” if you are so inclined. |
Operation (PPSA) | Text/Number Dropdown List suggested | See below |
The “Operation (PPSA)” Field
If you include this special field and populate it with some very specific values, you can use the task plan to:
Complete tasks
Uncomplete milestone tasks and the milestones linked to them
Update the remaining time for a task based on the value in another field (e.g. “Last PM Update for Hours Remaining” or the “Remaining Minutes (PPSA)” field if it’s not defined as read-only)
Completing a task
Setting a task to “Completed” from the task plan is accomplished by:
Set the value of the Operation (PPSA) field to “Complete()”
Save the task plan
After you’ve saved and subsequently refreshed the task plan frame by using the built in Smartsheet refresh behind the vertical ellipse, refreshed the entire page, or manually “Sync”ing the task plan, you will see the task marked as completed in time entry, and set to 100% complete in the task plan if you are showing the “% Complete (PPSA)” field.