Control | Description | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Any resource | Anyone can enter time, excluding resources with the limited access flag enabled who must have an assigned role | |||||||||||
Resources assigned to a role | Only resources that are explicitly requested or booked to this project can submit hours. Even if the number of hours is zero. This is useful when you have a specific team and only that team should be working on this project. | |||||||||||
Resources in cost center | Any resource under the specified cost center as of today, can enter time. Excluding resources with the limited access flag enabled who must have an assigned role. | |||||||||||
Resources may report time only to assigned tasks | This setting is only available if the Detailed Task Management checkbox is ticked under the Project Management section (see further down in this help document for a fuller explanation). When ticked, only resources who are assigned to a particular task can submit time against it. | |||||||||||
Require Descriptions on Timecards | All resources must include a description for each time card submitted. Time cards without descriptions will be automatically rejected and returned to the resource for correction. | |||||||||||
Open for Time | Allow time to be reported for work done on this project. By default, the current stage determines this setting. However, you can override the setting if need be. | |||||||||||
Open for Time Transfers | Allow time cards to be transferred onto this project. By default, the current stage determines this setting. However, you can override the setting if need be. | |||||||||||
Time Approvers | Open the drop-down menu to choose who will be responsible for approving time cards submitted to this project.
|
...