The area is reached by opening a project and choosing the Task Planning tab.
Child pages (Children Display) | ||||
---|---|---|---|---|
|
...
- the PM thought it would take forty hours
- task should be completed by Tuesday
- So far the resource has entered 44
- The resource reports that the task requires 5 more hours to complete
- . Now when the PM looks at the Task Status tab for a visualization of task performance, he will see that the task has gone over budget, but is nearly complete.
...