This is the primary cause of problems. Simply switch the Display In dropdown box to the correct mode for this project. See screenshot below.

Image Added

What are weekly and daily mode?

Resources can be scheduled by the day or by the week. In fact, you have cell-by-cell control over this. So Jimmy can be scheduled by the day for February and then by the week thereafter, or any combination thereof. You can switch between the two modes via the Display In dropdown box. If you choose Hybrid, you can do both at once.

Image Removed 

If resources are in the wrong scheduling mode, simply right click their role and choose Change Scheduling Mode.

...

On the Project Roles Tab and Role Info Tab you can set start and end dates. Cells outside those dates will be grayed out.

 

Project Start and End Dates

On the Project Info Tab you can set start and end dates. You can't schedule outside these dates.

 

View Mode

You may be unable to request or book hours because the project is opening in View Only mode. To check if this is the case, simply look at the project window title bar. If it reads – View Project, then you won't be able to enter hours. You probably need to change the project stage or edit your permissions to get edit access.

Image Added