Projects configured for “Projector Task Management Classic”, formerly known as “Detailed Task Management” will see in information panel instead of an embedded task planning interface.

...

Linking - What happens when a project is Smartsheet enabled?

The System (Projector) does some behind the scenes magic when the project is created and each time the project setup is saved with a new template.

  • A new Smartsheet “sheet” is generated from the selected Smartsheet template 

  • The current Projector project is then linked to the newly created Smartsheet sheet

  • A Smartsheet <> Projector “sync” is executed to push project data to the sheet and sheet data to the project

...

Two-Way Syncing - How does it work?

  • Projector project data → Smartsheet sheet (task plan)

    • Working days and holidays 

    • Role updates (assignments are cleared if a role is missing)

    • Task type updates (task types are cleared if a type is missing)

    • Updated role resource assignments

    • Task % complete (future enhancement)

    • Undeleted & repaired tasks in necessary

  • Smartsheet planning data → Projector project

    • Task name & duration

    • Task assign to (role) & allocation %

    • Task start and end date (duration is calc’d by Projector)

    • Task type

    • Open/closed for time

  • Projector does some work behind the scenes

    • Makes task plan data available to:

    • Emails are generated as appropriate

...

Time Entry

Tasks from the task plan will appear automatically on the resource’s timesheet for time to be entered against them.

...