Linking - What happens when a project is Smartsheet enabled?
The System (Projector) does some behind the scenes magic when the project is created and each time the project setup is saved with a new template.
A new Smartsheet “sheet” is generated from the selected Smartsheet template
The current Projector project is then linked to the newly created Smartsheet sheet
A Smartsheet <> Projector “sync” is executed to push project data to the sheet and sheet data to the project
...
Two-Way Syncing - How does it work?
Projector project data → Smartsheet sheet (task plan)
Working days and holidays
Role updates (assignments are cleared if a role is missing)
Task type updates (task types are cleared if a type is missing)
Updated role resource assignments
Task % complete (future enhancement)
Undeleted & repaired tasks in necessary
Smartsheet planning data → Projector project
Task name & duration
Task assign to (role) & allocation %
Task start and end date (duration is calc’d by Projector)
Task type
Open/closed for time
Projector does some work behind the scenes
Makes task plan data available to:
Budgeting
Reporting
BI tool use
… and the rest of Projector
Emails are generated as appropriate
...
Time Entry
Tasks from the task plan will appear automatically on the resource’s timesheet for time to be entered against them.
...