Info | |||||
---|---|---|---|---|---|
To see your utilization data at the project level you will want to switch from the Utilization report to the Ginsu report. This is one of Projector's most often asked questions. It seems like a simple request. Projector has utilization information. For instance, Charlie has 70% billable utilization and 30% non-billable utilization. Let's break his billable utilization up by project and see where that 70% is coming from. However, when you go to run your utilization report, no project fields are available. Why?!!! To explain, you first need to be absolutely clear that utilization is a concept at the whole resource level. It can only successfully compute when looking at an individual person or a group of individuals. This tells you useful information such as Charlie is overworked, or the creative department is underutilized. What you can't do is compute utilization on a project. The problem is that projects aren't people. Projects can be over budget, they can be under budget, but they can't be 110% utilized. Another way to frame it is like this - if Sally is overutilized because she works 20 hours on one project and 30 hours on another, which project was responsible for her being overutilized? Project Projector has a way of answering this question, just framed in a different way than you were expecting. To get started, let's introduce two concepts in our reporting. We call them Above the Resource and Below the Resource.
|
...