Role - Status

Role - Status

Role Status tells you where a role is in the workflow between "someone needs to be staffed" and "the right person is locked in with the right hours." Projector calculates Role Status automatically based on the role's hours data and who currently owns the role. You do not set it manually — it updates as you and your team work the role.

 

Role Status is shown on the Role landing page, in Role Search results, and in scheduling views throughout Projector Web.

Permissions and Settings

The following people can view Role Status:

  • cost center permission View Projects - can view all roles on these projects

  • anyone on the PM Team - can view all roles on their projects

  • users with a role shared to them - can view shared roles only

  • resources who are allowed to request or book themselves - can view only their own roles

 

Role Status is read-only. It changes as a result of user actions on the Role - Resource Assignment and Role - Schedule tabs.

The Four Statuses

Status

What it means

When a role lands here

Status

What it means

When a role lands here

Not Scheduled

Demand exists; no hours yet

The role has been created with no requested or booked hours.

Request in Process

A project manager has placed a request that schedulers have not yet fulfilled

Requested hours don't match booked hours, or the role is unnamed with booked hours; the role is owned by PMs.

Scheduling in Process

Schedulers are actively working the request

The PM has submitted the role, or schedulers have routed it to themselves.

Scheduling Complete

The request has been fulfilled — booked hours match the request and a named resource is in place

A scheduler has approved, rejected, or finalized the request.

Roles that have been deleted are shown with a status of Deleted in Projector Web. Deleted roles are not included in default Role Searches unless Show deleted roles is enabled.

What "Needs Attention" Really Means

A role appears on the Roles Needing Attention default search when either of the following is true:

  1. Requested hours ≠ booked hours. There is a pending request that has not been fully fulfilled by schedulers.

  2. The role has booked hours but no named resource. Time has been scheduled against an unnamed role.

Both conditions are calculated from the role's own data. You do not need to flag a role manually, and you should not need to maintain a separate field to surface roles that need staffing.

⚠️ Common mistake — do not assign generic placeholder resources to roles you want to track.

Some users try to make unnamed roles "visible" by assigning a generic placeholder resource — for example, Generic Developer or TBD Architect — to the role. This hides the role instead of surfacing it. Once a role is named (even with a placeholder), and its booked hours match the requested hours, Projector treats it as Scheduling Complete and removes it from Roles Needing Attention.

The correct pattern is to leave the role unnamed and populate the role's criteria (cost center, title, department, location) using the Role Type. Schedule hours as needed for capacity planning. The unnamed-with-hours condition is exactly what puts the role on the Roles Needing Attention search.

Role Ownership: PMs vs. Schedulers

Every role is owned by either project managers or schedulers. Ownership is not visible as a column in most Role Search views, but it determines whether an active role displays as Request in Process (PM-owned) or Scheduling in Process (scheduler-owned).

Ownership flips automatically based on the action taken on the role:

Action

New ownership

Action

New ownership

PM creates a role

PMs

Scheduler creates a role

Schedulers

Submit

Schedulers

Approve, Reject, Finalize

PMs

Route to PMs

PMs

Route to Schedulers

Schedulers

Editing hours, renaming, updating rates

No change

 

💡 Tip: As long as your team uses the proper actions — Submit, Approve, Reject, Finalize, and Route to — rather than editing hours sideways, Role Status and ownership take care of themselves. There is no separate status field to maintain.

Status Transition Reference

The table below shows how each common user action affects Role Status and ownership.

 

User action

Status before

Status after

Ownership after

User action

Status before

Status after

Ownership after

Create role with no hours

—

Not Scheduled

Whoever created it

PM enters requested hours

Not Scheduled

Request in Process

PMs

PM submits the role to schedulers

Request in Process

Scheduling in Process

Schedulers

Scheduler approves the request

Scheduling in Process

Scheduling Complete

PMs

Scheduler rejects the request

Scheduling in Process

Scheduling Complete

PMs

Scheduler finalizes (partial fulfillment)

Scheduling in Process

Scheduling Complete

PMs

Route to PMs

Any active state

Request in Process

PMs

Route to Schedulers

Any active state

Scheduling in Process

Schedulers

Assign a named resource and align hours

Request in Process

Scheduling Complete

(depends on action used)

Edit hours, rename role, change rates

(Recalculated from data)

(Recalculated from data)

No change

For details on the request lifecycle actions, see Role - Schedule.

Frequently Asked Questions

A role I want to staff doesn't show up on Roles Needing Attention. Why?

The most likely cause is that the role has been assigned a generic placeholder named resource (see the warning above). Once the role is named and the requested hours match the booked hours, Projector treats the role as Scheduling Complete and removes it from the search. To surface the role, use the Swap action to replace the placeholder with the real resource — or remove the placeholder so the role becomes unnamed again.

A role still shows on Roles Needing Attention after I assigned a real resource. Why?

The most likely cause is that requested hours and booked hours do not match. Open the Role - Schedule tab and review both. The scheduler should use Approve or Finalize to align the booking and complete the workflow.

Can I manually set a role to Scheduling Complete?

No. Role Status is derived from the role's hours data and ownership. To move a role to Scheduling Complete, complete the request workflow: a scheduler must Approve, Reject, or Finalize the request. If the role is no longer needed, use Close out role.