Project - Draft Schedules

Project - Draft Schedules

Draft Schedule

You can now create multiple draft schedules for a single project, each with different configurations of resources, rates, and hours. Projector calculates profitability data for each draft using system-defined billing and cost rates, allowing you to compare scheduling options directly within the platform.

Once a draft schedule is selected, you can copy part or all of the data into the current project schedule. This streamlines the process and reduces the potential for errors.

Use Draft Schedule

1.     Enable the feature in the project landing page

Draft Schedule is available in all project setups.

The Enable Draft Scheduling option is automatically turned on for all existing and new accounts. You no longer need to adjust account-level settings — the only setup required is within the Project Setup screen.

To enable in a specific project:

  1. Go to Project Setup → Scheduling.

  2. From the dropdown, select Enable Draft Scheduling.

This update removes the need for manual configuration in Account Settings and makes Draft Scheduling accessible by default to all project managers.

Picture2-20250616-135647.png

2.     Create a draft schedule

Picture3-20250616-135724.png
Picture4-20250616-135803.png

●       “No hours” option always exists.  If the project has requested or booked hours, then they can also be used to create the draft schedule.

●       Start Date needs be the first day of the week while End Date needs to be the last day of the week.

Permissions: any user who can edit requested or booked hours can edit draft hours

Picture5-20250616-140148.png

:bulb: Tip - Before creating different scheduling plans, add the roles being considered to the project with applicable billing rate and cost rate.  For example, if you are to compare the US east coast resource plan vs. the west coast resource plan, add resources from both plans to the project.  After creating draft schedules, you can disable roles that do not apply to the resource plan you are working on.  Please note: disabled roles’ draft hours will be cleared.

:bulb: Tip - To show disabled roles, use “Show disabled roles …” setting in the grid configurator

Picture6-20250616-140358.png
Picture7-20250616-140435.png

3.     Add draft hours

You can make multiple edits at once using the new multi-cell edit feature.

  • Click the blue arrow next to a resource’s name to select all columns for that resource.

  • Click blue arrows for multiple resources to apply updates across their entire rows.

  • You can hold Ctrl (Control) to deselect individual cells within your selection.

  • The total number of selected cells appears above the gear icon on the toolbar.

After selecting cells:

  • Right-click and choose Edit Selections to change values in bulk.

  • Or use the Fill From menu to auto-populate hours from existing data, including:

    • Available Hours

    • Requested Hours

    • Booked Hours

    • Task Hours or Remaining Task Hours

After editing, click Save & Recalculate to confirm changes.

Differences between draft and current schedule hours are highlighted in the grid to help you review before committing.

Picture8-20250616-140507.png

Draft hours can be entered manually in the cells or using the “Fill Special” feature. 

Picture9-20250616-140540.png
Picture10-20250616-140616.png

After entering draft hours for the roles, click “Save & Recalculate” to save the draft schedule. If there is a difference between the requested or booked hours on the current schedule and the draft hours, the differences will be highlighted in the search grid and above the grid. This helps prevent unintended overrides of current schedule data when the draft schedule is committed.

4.     Commit a draft schedule

Picture11-20250616-140643.png

The commit process includes improved conflict messaging and the ability to clear conflicts directly within the workflow.

When committing a draft schedule to booked or requested hours, any conflicts (such as overlapping dates, inactive roles, or locked periods) appear directly in the commit window.

To commit a draft schedule:

  1. From the Draft Schedule tab, click Commit Draft Schedule.

  2. Choose whether to commit as Booked Hours or Requested Hours.

  3. Review any highlighted conflicts and select Clear Conflicting Hours to resolve them.

  4. Click Commit to apply changes.

These enhancements improve transparency and reduce the steps needed to finalize project schedules.

Tip: You can also review draft schedule data in project reports and dashboards.

The Budgets tab and the Draft Schedule grid display key metrics—such as hours, cost, and profitability—helping you evaluate which draft to commit.

For broader analysis, select your draft schedule in Project Setup → Enable Draft Scheduling → Draft Schedule for Reports, then run reports like the Resource Schedule report to view that draft’s data.

Permissions: Users with permission to edit booked hours can commit draft hours as booked hours, while those with permission to edit requested hours can commit them as requested hours. Essentially, committing draft hours is simply an efficient way to update booked or requested hours.

5.     Add & delete a Draft Schedule

Picture12-20250616-140733.png

In addition to use the current schedule to create draft schedules, user can also create draft schedules based on existing draft schedules.

Picture13-20250616-140806.png

6.     View resource schedules using draft hours

Picture14-20250616-145516.png

First, select the draft schedule to be used in the reports in the project landing page. In R30, we added this feature to the Resource Schedule report and may add it to additional reports.

Picture15-20250616-145550.png

Second, if “draft schedule hours” is selected, this report will use the hours from the chosen draft schedule (in project landing page) or booked hours from the current schedule if no draft schedule is selected.

7.     View the financial impact

Measure against budget baseline:

Picture16-20250616-145744.png

Select a draft schedule or the current schedule to measure it against a time budget baseline. This provides a straightforward way to evaluate the financial impact of different resourcing plans.

In the draft schedule grid:

Picture17-20250616-145842.png