Error - Unable to save resource because there are multiple time off records

When editing a resource's scheduled time off you may receive the following error message on save: Unable to save resource because there are multiple time off records with the same date and time off reason, or more than 24 hours are scheduled on a given date.

Solution 1

The error message gives the impression that two different things can be causing this problem, but really there is just one root cause. More than 24 hours of time on a is scheduled on a single day. One reason for this is if you are using full-day time off and have overlapping dates. Another possibility is that you are using partial time off, but the sum of the partial time off on a particular day is greater than 24 hours.