Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Tip
titleFallback Approval

Fallback approval occurs when the someone cannot approve a time card and there are no other time approvers. For example, Sally is the project manager and a project is set to PM approval. Sally is not allowed to approve her own time. If Sally cannot do it, who can? Projector uses fallback approval. The fallback approvers consist of the following people:


In the unlikely event that there are no fallback approvers, the time will be stranded. There are two three ways to get it approved:
  1. Add an approver either to the resource's profile or give cost center permissions
  2. Add an approver through cost center permissions
  3. Have an administrator with the cost center permission Administer Time Workflow override it to approved

...