This structure contains the complete set of information about a project role (less any subordinate entities)task. The structure is used both to retrieve detailed project role task information and to pass information about a project role task back to the server to get updated.
...
Panel | ||
---|---|---|
| ||
|
Elements
Element | Data Type | Required? | Default | Description | Sample Data | |
---|---|---|---|---|---|---|
ExternalSystemIdentifier | String (50) | On Insert: No On Update: One of ExternalSystemIdentifier or ProjectTaskUid is required | The external system identifier is a unique identifier for a project task (may be null, but once set can only be updated to a different, non-null value). When both ExternalSystemIdentifier or ProjectTaskUid are missing or invalid, a new project task will be createdSpecify null when creating new tasks. | |||
ProjectTaskId | Int32 | No | Project task id is a unique identifier for a project cost baseline. For internal use only. | |||
ProjectTaskUid | Int64 | See ExternalSystemIdentifier | A unique and immutable identifier for a project task. When both ExternalSystemIdentifier or ProjectTaskUid are missing or invalid, a new project task will be createdSpecify null when creating new tasks. | 1152921504608747355 | ||
CompletedFlag | Boolean | No | false | If set to 'true', task status is set as completed. | false | |
Description | String (1000) | No | The description of the task. | |||
DurationMinutes | Int32 | No | 0 | The duration in minutes of the task. | 12000 | |
EarliestStartDate | DateTime | No | The earliest start date of the task. | 2018-01-31z | ||
FullWbsCode | String | No | ??? | Luke, it seems that when wbs code is missing, the task is inserted based on parent task, sibling task ..., but I could not pin down the rules hereThe full wbs code of the task. Only used in retrieving the project task. | 4 | |
NewExternalSystemIdentifier | String (50) | No | The new external system identifier of the updated or new task. | |||
OpenForTimeFlag | Boolean | No | true | If set to 'true', this task is open for time entry. | true | |
ParentTaskIdentity | No | The identity of the parent task. Click here for more information. | ||||
PlannedEndDateTime | DateTime | No | The planned end date of the task. | 2018-03-05z | ||
PlannedStartDateTime | DateTime | No | The planned start date of the task. | 2018-03-01z | ||
Predecessors | No | The predecessor predecessors of the task. Click here for more information. | ||||
PreviousSiblingTaskIdentity | No | The previous sibling of the task. Can be used to reorder the task among its siblings. Click here for more information. | ||||
ProjectTaskTypeIdentity | No | The task type of the task. Click here for more information. | ||||
TaskName | String (512) | Yes | The name of the task | Created from WS | ||
InheritPurchaseOrderNumberFlag | Boolean | On Insert: No On Update: No | true | If set to 'true', project inherits the purchase order number from the project role. | true | |
PurchaseOrderNumber | String (50) | On Insert: No On Update: No | Project role's purchase order number | The purchase order number associated with this project task. Specify only if not inheriting the purchase order number from the project role. | PO-004 | |
Subscriptions | No | The user users who receives notification on the task. Applies to milestone and not open for time tasks. Click here for more information. | ||||
UserDefinedFields | No | The user defined field fields associated with this task. Click here for more information. |
...