Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Info

Full Time Equivalents, Resource Equivalents, and Headcount are all different ways of looking at utilization in your organization. They fulfill unique roles and answer different business questions. This page will help you learn what each one does and when you are likely to choose one over the other.

 


Full Time Equivalents (FTEs)

...

In addition, because of the way pivot tables aggregate data, if you are breaking the data up by row fields, and the resource switches in the middle of a time bucket, they will get double counted. For example, you are looking at headcount by Title by month. Sarah's title changes from Manager to Sr. Manager one month. This will generate two rows and her headcount will be 2 for that month.